74017 REL 48: 2007-127-00 EXP E FORK OF S FORK SALMON PASSAGE RESTORATION |
|
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Full Name | Organization | Write Permission | Contact Role | Work Phone | |
---|---|---|---|---|---|
Marcie Carter | Nez Perce Tribe | Yes | Administrative Contact | marciec@nezperce.org | (208) 621-3534 |
Desmond Gelman | Bonneville Power Administration | Yes | CO Assistant | dxgelman@bpa.gov | (503) 230-4960 |
David Kaplowe | Bonneville Power Administration | Yes | F&W Approver | djkaplowe@bpa.gov | (503) 230-5365 |
Wesley Keller | Nez Perce Tribe | Yes | Contract Manager | wesleyk@nezperce.org | (208) 634-3031 |
Matthew Schwartz | Bonneville Power Administration | Yes | COR | mdschwartz@bpa.gov | (503) 230-4225 |
Carolyn Sharp | Bonneville Power Administration | Yes | Env. Compliance Lead | casharp@bpa.gov | (503) 230-5206 |
Emmit Taylor, Jr. | Nez Perce Tribe | Yes | Supervisor | emmitt@nezperce.org | (208) 621-3544 |
Karen Wolfe | Bonneville Power Administration | Yes | Contracting Officer | ktwolfe@bpa.gov | (503) 230-3448 |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Provide Environmental Compliance Documentation to BPA | A: 165. Provide Environmental Compliance Documentation to BPA | 08/01/2020 | 09/30/2020 | |
Effective implementation management and timely contract administration | B: 119. Project Management, Coordination, and Administration | 03/31/2021 | 03/29/2021 | |
Watershed and Habitat Restoration Outreach and Education | C: 99. Public outreach and education | 03/31/2021 | 03/22/2021 | |
Maintain riparian plantings at Wapiti and Burgdorf Meadows | D: 198. Maintain Riparian plantings at Wapiti and Burgdorf Meadows | 11/30/2020 | 09/30/2020 | |
Remove reed canary grass at Wapiti Meadows | E: 198. Remove Reed Canary Grass | 10/31/2020 | 09/27/2020 | |
Plant riparian vegetation at Forstrum Creek to stabilize banks | F: 47. Plant vegetation to stabilize banks and provide riparian cover on Forstrum Creek. | 11/30/2020 | 09/08/2020 | |
Decommission 14-16 Miles of Forest Roads on the Boise National Forest in Two-Bit Creek | G: 33. TwoBit-Sixbit Project Area Road Decommissioning of 14-15 Miles of Forest Roads | 11/30/2020 | 11/30/2020 | |
Decommission 1.6 miles of the 474 road | H: 33. Decommission 1.6 miles of the NFSR 474 road | 11/30/2020 | 09/30/2020 | |
Produce two AOP culvert designs on Profile Creek | I: 175. Produce AOP design on Two-bit Creek Culvert | 02/28/2021 | ||
GRAIP Road Surveys complete | J: 115. GRAIP road inventory surveys | 11/30/2020 | 11/30/2020 | |
mprove the Warren Wagon Road (gravel, shape, cross drains) so that sediment delivery to Long Gulch is reduced | K: 38. Long Gulch Road Improvement Project | 11/30/2020 | 08/31/2020 | |
Design two AOP structures on Profile Creek crossings | M: 175. Design two AOP structures on Profile Creek | 01/31/2021 | 01/31/2021 | |
Remove invasive weeds | N: 199. Remove Invasive Weeds from the SFSR and BC Watersheds | 11/30/2020 | 07/31/2020 | |
Review of proposed partner actions | O: 122. Review of Proposed Partner Actions | 03/31/2021 | 03/29/2021 | |
List of Selected FY2021 Restoration Implementation Projects | P: 114. Identify and Select FY2021 Restoration Projects | 02/28/2021 | 02/28/2021 | |
Planning/coordinating with agencies to ensure high quality watershed restoration | Q: 191. Coordinate with other agencies on watershed restoration projects | 03/31/2021 | 03/29/2021 | |
FY 2020 Progress Report | R: 132. Submit Progress Report for 4/1/2020 - 3/31/2021 | 03/31/2021 | 03/29/2021 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | Provide Environmental Compliance Documentation to BPA | |||||||
B | 119 | Project Management, Coordination, and Administration | |||||||
C | 99 | Public outreach and education | |||||||
D | 198 | Maintain Riparian plantings at Wapiti and Burgdorf Meadows | 09/09/2020 | ||||||
E | 198 | Remove Reed Canary Grass | 09/09/2020 | ||||||
F | 47 | Plant vegetation to stabilize banks and provide riparian cover on Forstrum Creek. | 09/09/2020 | ||||||
G | 33 | TwoBit-Sixbit Project Area Road Decommissioning of 14-15 Miles of Forest Roads | 09/09/2020 | ||||||
H | 33 | Decommission 1.6 miles of the NFSR 474 road | 09/09/2020 | ||||||
I | 175 | Produce AOP design on Two-bit Creek Culvert | 05/13/2020 | ||||||
J | 115 | GRAIP road inventory surveys | 05/13/2020 | ||||||
K | 38 | Long Gulch Road Improvement Project | 09/09/2020 | ||||||
L | 184 | Install Aquatic Organism Passage Structure on Jeanette Creek | |||||||
M | 175 | Design two AOP structures on Profile Creek | 05/13/2020 | ||||||
N | 199 | Remove Invasive Weeds from the SFSR and BC Watersheds | 09/09/2020 | ||||||
O | 122 | Review of Proposed Partner Actions | |||||||
P | 114 | Identify and Select FY2021 Restoration Projects | |||||||
Q | 191 | Coordinate with other agencies on watershed restoration projects | |||||||
R | 132 | Submit Progress Report for 4/1/2020 - 3/31/2021 | |||||||
S | 185 | Periodic Status Reports for BPA |